- Stage 1 – Preliminary – 2 Weeks
- Select/design floor plan
- Site inspection with project manager
- Quotation:
- Inclusions list
- Preliminary plans
- Timeframe & payment schedule
- Master Builders Residential Building Contract
- Stage 2 – Contract – 12 Weeks
- Sign contract and pay 5% deposit
- Council applications are submitted
- Materials selection
- Council approvals received
- Stage 3 – Commencement – 4 Weeks
- Fabrication of materials
- Earthworks/concrete slab laid
- Stage 4 – Lock Up – 6 Weeks
- Construction of frame
- Windows and doors installation
- Wall and roof insulation and cladding installation
- Stage 5 – Completion – 10 Weeks
- Internal fit out
- Site tidy up and builders clean
- Council final inspection
- Practical completion handover